Work on six main lines and one spur route is the big interstate system will account for 49 of the'projects at an estimated cost of 103 million dollars. Thirty-six pri mary projects will cost 26 million and 41 secondary projects 6 million dollars.There are 12 urban projects listed at a cost of 7.5 million dollars. Work along Interstate Routes 81 and 64 will be further accelerated in 35 new projects. These include major segments of 1-64 in the Norfolk,Richmond and Covington areas and on 1-81 in Rockbridge County north of Natural Bridge, in Augusta County north of Staunton and in Shenandoah County.

Work on Interstate 85 will extend the construction to US 58 in Mecklenburg Countv.