occurs In the PE system during the, winter. A new peak demand was established in the PE area December 19. The district manager also emphasized that the interconnection will help PE “hold the line" on electric rates.. Steel towers carry the line eight miles from PE’s halfmillion-dollar substation at Doubs, Md., to the Dickerson generating plant. They are the first stefel towers used for a major transmission project in the PE system. Most of the line has been constructed for double circuit. Initially, however, only one 230,000-volt circuit is being