But according to Resident Engineer Bob Moore and local maintenance supervisor Doug Bywaters, the improvement project went through the standard - and public - approval process.
During the update of the six-year plan in the winter of 1983-84, Rt. 630 was designated for “spot improvements” costing $10,000 and the work was scheduled for 1988-89, Mr. Moore reported. Then in fiscal year 1987, when the plan was undergoing its required bi-annual review, the scope of the Rt. 630 project was expanded to complete rebuilding with