Department of Correction's agreement to allow a reduction in the number of heads on a new sprinkler system.
That sprinkler system—set at $8,000 in the data sheet supplied Thursday—is just one of the items responsible for the $50,000 hike, according to Spencer.
Department of Correction's standards require installation of institutionaltype plumbing fixtures which are priced ‘‘abnormally high,” he said. The heating system must be replaced "instead of reworked as 1 originally thought,” Spencer added.
According to Smoot’s estimates, plumbing and heating work alone will cost $24,000 while improvements to the electrical system will add another $12,300.
The official in Fauquier who administers Rappahannock’s building inspection program has stipulated that a ramp for wheelchairs must be provided, adding an unexpected $4,500 to $5,000, the architect said. He noted that State Department of Corrections representatives say the ramp isn’t necessary since cell doors aren't wide enough to allow a wheelchair through.
"So we’re paying for access tor handicapped visitors,” Spencer pointed out.
The $115,000 doesn’t include cost of the heavy gauge 12-foot fence to en(Coniinued