Block · one region of the page, as the scanner read it. It may hold a whole story, part of one, several, or an advertisement; stitching blocks into articles is the next step. Text is supplied OCR.
Page 14 · column 4 of 7 · from the scan, no model involved

ing and Urban Development (HUD) funds which, in combination, will pay for the project.
Chairman Dennis asked Cilimberg to contact the State Water Control Board in regard to the schedule change. He also said the Authority needed a formal letter from the engineering firm, signed by the engineer, to commit them to exact dales for the project.
The Authority, however, will not enter into final contract, member James White said, until “after we know we’ve got the (EPA) extention.”
Grant Anticipation Safe
Baumgardner discussed a letter from McGuire, Woods & Battle, bond counsel for the project, assuring Authority members a grant-anticipation loan for the project would not cause debt to Rappahannock County and its taxpayers should EPA default on reimbursement.