the new door from the shop leading into the corridor where two classrooms are to be added.

• the rolling counter screen at the concession stand outside the new gym.

• nine skylights in the new gymnasium and its lobby.

• new brick frame and roof over the exisiting canopy at the rear of the old gym.

Other cost cutting design changes presented by the architect were delaying the completion of the auditorium and substitutions of (1) double layer dry wall for plaster in some ceilings and (2) a lower grade pipe for the originally proposed cast iron where allowed by the building code.

Baughan Construction’s bid price holds for 30 days, through March 28, Superintendent Robert Estabrook

(Continued on Page 16)