right-of-way. Representatives of Allegheny Power and PJM Interconnection are currently seeking federal eminent domain authority (through FERC) to string the line.
Elizabeth O'Hara, the director of federal affairs for the National Trust for Historic Preservation, said its 277,000 members strongly supported implementation of an Environmental Impact Statement. “We’re deeply troubled by the substantial and longterm impacts these power lines would have on historic properties,” she said. “These rules are draconian and enormously complex. Sixty days comment on them is insufficient.”
90.0%