1405) and Route 605 intersection. The contractors have 30 days in 'Which to complete the project.

Nelco Manufacturing Corp., of Oklahoma City, Okla., was awarded contracts totaling $157,186 to make repairs to an Interstate 66 bridge in Fauquier County and two U.S. 29 bridges in Culpeper County.

The 1-66 bridge in Fauquier County crosses the relocated Route 55 near Delaplane. The two bridges in Culpeper County carry the U.S. 29 bypass across the railroad tracks south of the town of Culpeper. The contractor has 60 days to complete each project.

Donald H. Selvage Inc., of Amherst, was awarded a $128,195 contract to repair the eastbound- and westbound-lane Interstate 64 bridges across the CSX railroad tracks in Albemarle County. The bridges are located on the eastern slope of Alton Mountain.

The contractor has 60 days in which to complete the repairs.

The Culpeper district project contracts were among a total of 48 contracts having a value of $60.4 million awarded for work throughout Virginia.