Comparison of Bid to Architect’s Construction Cost Estimates item Description New roof at Elementary School Upgrade existing HVAC System at Elementary School Upgrade existing Electrical System at Elementary School Communications Upgrade Classroom addition at Elementary School New Auxiliary Gym for High School Sitework New Track at High School Storm Water Management Totals Est. Construction Cost November 2004 $895,000 $659,000 $288,000 $115,000 $582,000 $680,000 $156,000 $464,000 $3,986,000 Actual Bid March 2005 $1,207,000 $628,400 $465,000 Included in Electrical . $747,000 $1,333,000 Included in Gym $670,244 $51,000 $5,102,144

93.7%