VDOT

From Page A13

• 1-66 Gainesville interchange Phase 4: Route 29/Linton Hall Road

• 1-95 widening in Fairfax County from Newington to Occoquan

• Route 50 widening at the Fairfax/Loudoun County line

• Constructing six lanes of the Fairfax County Parkway from Rolling Road to Fullerton Road, in response to the BRAC effort

• Route 3 widening and Spotsylvania Courthouse bypass • • Route 11/460 in Roanoke County

• Port Republic Road in Rockingham County

• Route 3 widening in Culpeper County

• Route 360 in the Mechanics vi lie area and Chesterfield County

Improving access and land use -

• A bicycle and pedestrian path in Middlesex County

• 1-81 exit 150 at Troutville and exit 17 at Abingdon

• 1-66 multimodal study inside the Beltway

• Route 29 Long Range Corridor Plan in Culpeper district

• Route 37 Environmental Impact Study in Frederick County

The CTB also approved the Virginia Department of Transportation’s (VDOTs) first six-year program for maintenance and operations. The new program, which is required by legislation passed last year, is shown as part of the broader SYIP for transportation projects. The new $10.5 billion program includes $8.3 billion for maintenance and operations of interstate, primary and secondary state-maintained roads and $2.2 billion for payments to localities that maintain their streets.

The FY08 budgets for VDOT and the Virginia Department of Rail and Public Transportation DRPT also were approved at $4 billion and $624 million, respectively.

78.4%