Block · one region of the page, as the scanner read it. It may hold a whole story, part of one, several, or an advertisement; stitching blocks into articles is the next step. Text is supplied OCR.

Page 6 · column 3 of 6 · from the scan, no model involved

The clipping this text was read from
The clipping this text was read from

some anticipated additional interest funds of about $30,000 on the loan that can be dedicated to the track. The track is estimated to cost $550,000. The estimated amount of additional funds needed for the track = $469,000.

Hopefully, the bids will come in lower than projected. We can also look at constructing the asphalt track without the acrylic surface as a cost saving option.

Another option

Build the Elementary Addition that replaces all three modular units: $719,846

Re-bid and build the track: $550,000

Note: The committee considered relocating the auxiliary gym to the land the Supervisors just purchased behind the high school. This would require several months to re-design the gym to fit a new site and to re-bid the gym.

The committee estimates there would be additional site and access road costs associated with that. We also project that re-bidding the gym would result in higher construction costs for that structure. Therefore, the committee is not recommending that we relocate the gym.

96.4%